| Foundation |
|
Precast Reinforced Concrete Pile and/or other approved foundation system complying with SS CP4 |
Superstructure
& Substructure |
|
Reinforced concrete and/or post tensioned concrete structure complying with SS CP65 |
Roof |
|
Reinforced concreted and/or post tensioned concrete structure flat roof with waterproofing system |
Floor
Loading Capacities |
|
| 1st
storey (warehouse) |
= |
10.0
KN/m2 |
| 1st storey (mezzanine) |
= |
5.0 KN/m2 |
| 1st storey (canteen) |
= |
5.0 KN/m2 |
| 2nd to 3rd storey
warehouse) |
= |
7.5 KN/m2 |
| 4th to 8th storey
(factory) |
= |
7.5 KN/m2 |
|
Structure
Floor To Floor Height |
|
| 1st
storey |
= |
6.50
meters |
| 1st storey (mezzanine) |
= |
3.00
meters |
| 2nd to 3rd storey |
= |
4.00 meters |
| 4th to 8th storey |
= |
3.50 meters |
| |
|
|
|
Windows |
|
Aluminium
framed windows with tinted glass |
Doors |
|
- Timber doors with selected quality lock sets to Factory
and Warehouse units
- PVC doors with quality lock set to toilets |
External
Walls |
|
Reinforced
concrete and/or clay brick with cement and sand rendering and
emulsion paint finish |
Ceilings |
|
- Skim coat and/or off-form with paint finish to all units
- Plaster board and/or skim coat and/or off-form with paint finish to toilets |
Internal
Wall Finishes |
|
- Cement and sand plaster
and/or skim coat with paint finish
- Tiles and/or cement and sand plaster and/or skim coat with paint finish to lift lobbies
- Tiles and/or cement and sand plaster with paint finish to toilets |
Floor
Finishes |
|
- Power float and/or screed finish to Factory and Warehouse
units
- Tiles and/or power float and/or screed finish to lift lobbies
- Ceramic tiles to toilet |
Lifts |
|
- 4 service lifts
- 6 passenger lifts and 2 passenger cum fireman lifts |
| Electricial |
|
-
Emergency lighting including exit sign to all units provided in compliance with statutory requirements.
- 60A 3 phase power supply to meter compartment for all 2nd and 3rd storey warehouse
units except 100A 3 phase power supply for units #02/03-08, #02/03-21, #02/03-36, #02/03-49
- 60A 3 phase power supply to meter compartment for all 1st storey warehouse
units
- 200A 3 phase power supply to canteen |
| Telecommuncation
Services |
|
Local
box and pre-wired telephone cable up to telephone riser
duct will be provided to each factory/warehouse unit
to facilitate telephone connection upon application
by purchasers |
| Master
Antenna System (MATV) |
|
MATV
ready tap-out is provided |
Fire
Protection |
|
Fire protection system provided in compliance with statutory
requirements |
Sanitary
and Plumbing Installation |
|
Sanitary and plumbing system provided in compliance with statutory
requirements |
Mechanical
Ventilation |
|
Mechanical ventilation provided in compliance with statutory requirements to designated areas where natural ventilation is not possible |
Communication
System |
|
Communication system provided in compliance with statutory
requirements |
Lightning
Protection |
|
Provided in accordance with Singapore Standard Code
of Practice CP-33: 1996 |
Project
Information |
|
Zoning: Industrial Business 1
Tenure
of Land: 60 years leasehold w.e.f. 1st January 2007
Lot / Mukim: Lot No. 6179N of Mukim 23
Planning Approval No.: P160107-06F2-A011 dated 08th June
2007
Building Plan No.: A1525-00015-2006-BP01 dated 26th
June 2007
Expected TOP date: 3rd September 2014
Expected Date of Legal Completion: 3rd September 2017 |
| |
|
|